May 2025 - Project Update

28 May 2025

Beginning Monday, June 2nd, the Boulevard of the Allies will be closed at Parkview Avenue to accommodate reconstruction of the intersection. Traffic to Parkview Avenue will be detoured via Dawson St. and Oakland Square.

Work on the intersection will be conducted in two phases. During Phase 1, the east side of the intersection will be under construction and southbound vehicles on Parkview will be able to turn right on Boulevard of the Allies. During Phase 2 the west side of the intersection will be under construction and southbound vehicles on Parkview will have to continue through the intersection, or head north on Parkview.

Work at the intersection is expected to take 2-3 months.