Project Area
Existing Conditions
Traffic Data Collection
Traffic Summary
- Classification:
- Speed Limit: 25 mph
- Average Daily Traffic (ADT): 1,835 vehicles per day (VPD)
- 85th % speed: 35 mph
- Overall % speeding: 90%
Planned Improvements
- Six (6) speed tables
- Raised crosswalk
Construction Timeline
Construction begins April 19, 2023. One lane of traffic on Johnston Avenue will be closed to traffic, with flaggers stationed at each end in order to allow alternating traffic.
The duration of the project is expected to last five days, weather permitting. Hours of construction will be 7:00 a.m. to 5:00 p.m. Temporary no parking signage will be posted throughout the corridor where work is taking place.
Construction completed: April 20, 2023.