Background
The Department of Public Works (DPW), along with input from residents and community partners, is designing the implementing site and infrastructure improvements to Leslie Park in the Lawrenceville neighborhood.
Leslie Park is a 6.02-acre site with recreational amenities including a playground, spray feature, basketball court, parking lot, baseball fields and a decommissioned pool/ pool house structure. The site also houses the Boys and Girls Club building, but this building will not be included in the scope of work for this project.
A Conceptual Master Plan was developed by the Pittsburgh Parks Conservancy in 2015 and can be viewed below.

Project Scope
- Conversion of Pool/Pool House
- Demolition of existing pool and pool house
- Convert to usable community space
- Evaluate feasibility of preserving an ‘architectural artifact’ from pool house as community has connection to building
- Play Area Improvements
- Renovate existing playground equipment and safety surfacing to integrate with spray features.
- Evaluate site for best suited location for utilities, accessibility, etc.
- Parking Lot Improvements
- Consider entrance and access improvements
- Repave and restripe parking lot
- Consider options for optimizing accessibility
- Park Pavilion and Restroom Building
- Evaluate site for ideal location for facility
- Include two family restrooms
- Include shelter/picnic facility for playground/spray feature users
- Sports Court Renovation
- Evaluate the relevancy of the basketball court with the consideration of potential upgrades or conversion to alternative programming
- ADA Upgrades and Connections
- Ensure site-wide accessibility and connectivity through pathways or switchbacks, as necessary
- Lighting & Safety Improvements
- Evaluate condition of existing site lighting and identify needs for proposed lighting per the newly improved park amenities outlined above
- Stormwater Management
- Stormwater BMP’s should be included to meet the City’s Stormwater Management Code (see General Responsibilities for more information)
*Note: DPW will be renovating the ball fields in-house. The fields will not be included in the scope of work outside of pedestrian connections and wall repairs. Programming priorities listed above are intended as a general guide and will be confirmed with the community through a series of engagements.