Project Area
Existing Conditions
Traffic Data Collection
Traffic Summary
- Classification:
- Speed Limit: 25 mph
- Average Daily Traffic (ADT): 1,402 vehicles per day (VPD)
- 85th % speed: 33 mph
- Overall % speeding: 70%
Planned Improvements
- Speed tables
- Improved crosswalks with hi-vis piano keys and painted curb extensions
More detailed plans to follow once design is underway.
Construction Timeline
Construction work is tentatively expected to start on Wednesday, June 21, 2023. During the speed table construction one lane of traffic of Bailey Ave will be closed to traffic, with flaggers stationed at each end in order to allow alternating traffic.
The duration of the project is expected to last two (2) days, weather permitting. Hours of construction will be 7:00 a.m. to 5:00 p.m. Temporary no parking signage will be posted throughout the corridor where work is taking place.