Project Area

project area

Existing Conditions

existing conditions

Traffic Data Collection

Draft Plan

Traffic Summary

Classification: Collector
Speed Limit: 25 mph
Average Daily Traffic (ADT): 3,621 VPD (Vehicles per day)
85th % speed: 32 mph
Overall % speeding: 70%

Planned Improvements

  • A series of speed tables throughout the corridor
  • Pedestrian crossing improvements at bus stop locations
  • Parking lane lines to narrow field of vision and delineate space for parking

Construction Timeline

Construction work will now take place following final utility restoration.