Project Area
Existing Conditions
Traffic Data Collection
Traffic Summary
- Classification: Local
- Speed Limit:25 mph
- Average Daily Traffic (ADT): 2,135
- 85th % speed:31 mph
- Overall % speeding: 56%
Planned Improvements
- Pedestrian upgrades with high visibility crosswalks
- Four (4) speed humps
Construction Timeline
Construction is planned to start Wednesday, August 9th. Work is expected to last two (2) days, weather depending.
Pavement markings on the speed humps will be placed a day or two after actual construction. Signage, however, will be installed in advance of construction.
Construction completed: August 9, 2023.