Project Area
Existing Conditions
Traffic Data Collection
Application
Traffic Summary
- Classification: Local
- Speed Limit: 25 mph
- Average Daily Traffic (ADT): 7,802 vehicles per day (VPD)
- 85th % speed: 33 mph
- Overall % speeding: 76%
Planned Improvements
- Speed Tables or Speed Cushions
Construction Timeline
Construction is expected to begin May 24, 2023. One lane of traffic on Shady Avenue will be closed to traffic, with flaggers stationed at each end in order to allow alternating traffic.
The duration of the project is expected to last two (2) days, weather permitting. Hours of construction will be 7:00 a.m. to 5:00 p.m. Temporary no parking signage will be posted throughout the corridor where work is taking place.