Project Area

Existing Conditions

existing conditions

Traffic Data Collection

traffic data

Traffic Summary

Classification: Collector
Speed Limit: 25 MPH
Average Daily Traffic (ADT): 8,143 VPD (Vehicles per day)
85th % speed: 38 MPH
Overall % speeding: 97%

Planned Improvements

  • Speed tables throughout the project area
  • Additional pavement markings

Construction Timeline

Construction is expected to begin Wednesday, September 10th, and work is expected to last (2) two days. Asphalt work will be taking place on both days of installation.

There will be intermittent closures of Shady Avenue between Fifth and Hastings during asphalt construction. Through traffic should seek alternate route, but flaggers will be stationed to allow local traffic passage. Small travel delays are likely and should be anticipated.

Permanent signage will be installed in advance of construction. Permanent pavement markings will be installed in the days to follow.