Project Area
Existing Conditions
Traffic Data Collection

Traffic Summary
Classification: Collector
Speed Limit: 25 MPH
Average Daily Traffic (ADT): 8,143 VPD (Vehicles per day)
85th % speed: 38 MPH
Overall % speeding: 97%
Planned Improvements
- Speed tables throughout the project area
- Additional pavement markings
Construction Timeline
Construction is expected to begin Wednesday, September 10th, and work is expected to last (2) two days. Asphalt work will be taking place on both days of installation.
There will be intermittent closures of Shady Avenue between Fifth and
Hastings during asphalt construction. Through traffic should seek
alternate route, but flaggers will be stationed to allow local traffic
passage. Small travel delays are likely and should be anticipated.
Permanent signage will be installed in advance of construction. Permanent pavement markings will be installed in the days to follow.