October 2024 - Project Update

25 October 2024

As of October 25, all project activities that can be completed ahead of the truss installation are now complete.

This includes construction of the two new pier foundations and refurbishment of the existing abutments, removal of the old roadbed on Riverview Drive and stabilization of the ground in preparation for the new trail. On Davis Avenue, the stormwater system has been updated, overhead utilities have been relocated, and sidewalks have been rebuilt with improved accessibility.

As mentioned in the previous project update, there were supply chain issues procuring some of the rolled steel that makes up the bridge truss. However, the fabricator has confirmed receipt of all materials, and off-site fabrication is progressing with a delivery date scheduled for December 2024.

The contractor will be mobilizing in December to install the truss, but due to seasonal temperatures, crucial concrete and asphalt work will be delayed until Spring 2025.

We will continue to provide construction and schedule updates on this page as work progresses. In the meantime, we appreciate everyone's patience and cooperation with the on-going trail closures in Riverview Park.