Project Area

Mapped project area

Planned Improvements

  • Five (5) speed humps
  • Two (2) speed tables where transit operates on Schenley Avenue between Columbo and Mossfield
  • Line striping for parking delineation to prevent sidewalk parking
  • Pedestrian upgrades including intersection daylighting, crosswalk upgrades, and improved signage
  • Intersection improvements at Mossfield, Broad and N Mathilda to increase safety by formalizing turn lanes and daylighting to improve sight lines for turning vehicles and pedestrians

Traffic Data Collection

Traffic Data Collection
Traffic Data

Traffic Summary

N Mathilda Street

  • Classification: Local
  • Speed Limit: 25 mph
  • Average Daily Traffic (ADT): 551 vehicles per day
  • 85th % speed: 35 mph
  • Overall % speeding: 74%

Schenley Avenue

  • Classification: Local
  • Speed Limit: 25 mph
  • Average Daily Traffic (ADT): 1,121 vehicles per day
  • 85th % speed: 35 mph
  • Overall % speeding: 67%

Construction Timeline

Construction was completed mid-September 2024.